124k views
4 votes
20 men working 6 hours a day can finish a work during 10 days. 4 men got seek and didn't work How many hours a day should work other 16 men to finish the work during (a) 10 days? (b) during 15 days?​

2 Answers

5 votes

Explanation:

subs8biiisowm9bbbs9 to

User Klor
by
7.1k points
4 votes

Answer:

B) 15 days

Explanation:

Total Work = (Number of men) x (Hours worked per day) x (Number of days)

Using this formula, we can find the total amount of work to be done in the scenario given in the question:

Total Work = (20 men) x (6 hours per day) x (10 days) = 1200 hours

(a) To find out how many hours a day the remaining 16 men should work to finish the work in 10 days, we need to subtract the work that was not done due to the absence of the 4 men:

Remaining Work = Total Work - Work not done by 4 men

Remaining Work = 1200 - (4 men) x (6 hours per day) x (10 days)

Remaining Work = 840 hours

To finish the remaining work in 10 days, the 16 men would need to work:

Hours per day = Remaining Work / (Number of men) x (Number of days)

Hours per day = 840 / (16 men) x (10 days)

Hours per day = 5.25 hours

Therefore, the 16 men would need to work 5.25 hours per day to finish the work in 10 days.

(b) To find out how many hours a day the remaining 16 men should work to finish the work in 15 days, we need to calculate the total amount of work that needs to be done each day:

Daily Work = Total Work / Number of days

Daily Work = 1200 / 15

Daily Work = 80 hours

To finish the daily work of 80 hours, the 16 men would need to work:

Hours per day = Daily Work / Number of men

Hours per day = 80 / 16

Hours per day = 5 hours

Therefore, the 16 men would need to work 5 hours per day to finish the work in 15 days.

User Evan Frisch
by
6.8k points