How you find the applied overhead

1 Answer

10 votes

Answer:

Multiply the overhead allocation rate by the actual activity level to get the applied overhead for your cost object. If your overhead allocation rate is $100 per machine hour, then multiply $100 times the number of machine hours for a particular product to get its applied overhead.