50.4k views
5 votes
Performing _____ involves monitoring specific project results to ensure that they comply with the relevant quality standards while identifying ways to improve overall quality.

User Chaunte
by
8.0k points

2 Answers

3 votes

Answer:

D.ensuring projects end on time through careful planning and organization

Step-by-step explanation:

performing various statistical tests and suggesting methods to improve quality control.

User Bracadabra
by
8.5k points
5 votes
Performing controlling Quality involves monitoring specific project results to ensure that they comply with the relevant quality standards while identifying ways to improve overall quality.
This action often done by large corporations in order to make sure that all the products that they create at the operational stages meets the company's standard.