Match the risk mitigation techniques with their characteristics.

Tiles
Mitigate
Transfer
Avoid
Accept

Considering the negative impact involved in a
project and carrying it out in spite of the risks.
arrowBoth

Failing to do certain things to eliminate the
possibility of risks.
arrowBoth

Lowering the level of risks by making changes
in your plan.
arrowBoth

Moving the risk to another party or organization
that is ready to share the risk financially
or otherwise.
arrowBoth

1 Answer

6 votes
Avoid- Failing to do certain things to eliminate the possibility of risks.
Transfer-Moving the risk to another party or organization
that is ready to share the risk financially
or otherwise.
Accept-Considering the negative impact involved in a
project and carrying it out in spite of the risks.
Mitigate-Lowering the level of risks by making changes
in your plan.