Using time and materials pricing, what is the total price for a job requiring 2 direct labor hours and $59 of materials

User Stiegi
by
4.1k points

1 Answer

8 votes

Answer:

b. $221.5

Step-by-step explanation:

Note: The similar question is attached as picture below

Particulars Amount

Materials $62

Materials markup (25% of $62) $15.5

Direct Labor (2 Hours at $72 per hour) $144

Total price for Job $221.5