8.3k views
4 votes
Johnson Inc. is a job-order manufacturing company that uses a predetermined overhead rate, based on direct labor hours, to apply overhead to individual jobs.

For the current year, estimated direct labor hours are 95,000 and estimated factory overhead is $617,500.
The following information is for September of the current year:
September 1, inventories:
Materials inventory $ 7,500
Work-in-process inventory (All Job A) 31,200
Finished goods inventory 67,000
Material purchases 104,000
Direct materials requisitioned:
Job A 65,000
Job B 33,500
Direct labor hours:
Job A 4,200
Job B 3,500
Labor costs incurred;
Direct labor ($8.50/hour) 65,450
Indirect labor 13,500
Supervisory salaries 6,000
Rental costs:
Factory 7,000
Administrative offices 1,800
Total equipment depreciation costs:
Factory 7,500
Administrative offices 1,600
Indirect materials used 12,000
Job A was completed during September and Job B was started but not finished.
Required:
1. What is the total cost of Job A?
2. What is the total factory overhead applied during September?
3. What is the over-applied or under-applied overhead for September?

User Eight Rice
by
8.0k points

1 Answer

5 votes

Answer:

1. $159,200

2. $50,050

3. $4,050 overapplied

Step-by-step explanation:

1. Calculation for The total cost of Job A?

TOTAL COST OF JOB A

Direct materials requisitioned $ 65,000

Add Direct labor costs $ 35,700

(4,200 hours * $ 8.50 per hour)

Add Applied overheads $ 27,300

(4,200 hours * $ 6.50 per hour)

($617,500/95,000=$ 6.50 per hour)

Add Work in process $ 31,200

Total Cost of Job A $ 159,200

Therefore Total Cost of Job A will be $ 159,200

2. Calculation for What is the total factory overhead applied during September

First step is to calculate Predetermined Overhead Rate

Predetermined Overhead Rate=$617,500/95,000

Predetermined Overhead Rate=$ 6.50 per hour

Now let calculate the total factory overhead applied

Total factory overhead applied =(Job A 4,200+Job B 3,500) × ($6.50)

Total factory overhead applied =7,700×$6.50

Total factory overhead applied =$50,050

Therefore the total factory overhead applied will be $50,050

3. Calculation for What is the over-applied or under-applied overhead for September

First step is to calculate Actual factory overhead

Actual factory overhead :

Indirect labor 13,500

Supervisory salaries 6,000

Rental costs:Factory 7,000

Factory 7,500

Indirect materials used 12,000

Actual factory overhead =$46,000

Second step is to calculate Predetermined Overhead Rate

Predetermined Overhead Rate=$617,500/95,000

Predetermined Overhead Rate=$ 6.50 per hour

Now let calculate the over-applied or under-applied overhead for September

Over-applied or under-applied overhead =(Job A 4,200+Job B 3,500*$ 6.50 per )-$46,000

Over-applied or under-applied overhead =(7,700*$6.50)-$46,000

Over-applied or under-applied overhead =$50,050-$46,000

Over-applied or under-applied overhead =$4,050 overapplied

Therefore the over-applied for September is $4,050

User HM Tanbir
by
7.6k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories