​a task that represents several activities is known as a _____.

1 Answer

1 vote

The answer is task group. Each task group represents several activities. It acknowledge complicated projects to be seen as a set of integrated modules. Task name a brief descriptive name for a task, which does not have to be unique in the project. Though, a task named make Interviews might appear in several level of the project.

User NickStoughton
by
7.8k points