Urgent Math Help Needed Please!!!!

Table attached Below

The table shows five activities (in days) for a project. Use PERT (Program Evaluation and Review Technique) to calculate the expected time of completion for activity B.

Question 2 options:

11 days


14 days


9 days


8 days

Urgent Math Help Needed Please!!!! Table attached Below The table shows five activities-example-1
User Drcocoa
by
7.9k points

1 Answer

3 votes

PERT =
(OT+4MLT+PT)/(6)

Activity B: OT = 3, MLT = 6, PT = 12

PERT =
(3+4(6)+12)/(6)

=
(3+24+12)/(6)

=
(39)/(6)

= 6.5