Urgent Math Help Needed Please!!!! Table attached Below The table shows five activities (in days) for a project. Use PERT (Program Evaluation and Review Technique) to calculate the expected time of completion
asked
Nov 15, 2019
192k
views
3
votes
Urgent Math Help Needed Please!!!!
Table attached Below
The table shows five activities (in days) for a project. Use PERT (Program Evaluation and Review Technique) to calculate the expected time of completion for activity B.
Question 2 options:
11 days
14 days
9 days
8 days
Mathematics
high-school
Drcocoa
asked
by
Drcocoa
7.9k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
3
votes
PERT =
Activity B: OT = 3, MLT = 6, PT = 12
PERT =
=
=
= 6.5
Oscar Nieto
answered
Nov 20, 2019
by
Oscar Nieto
8.3k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
← Prev Question
Next Question →
Related questions
asked
Nov 26, 2024
221k
views
What is the outcome of the statistical methodology used in the program evaluation and review technique (pert)? O focusing on individual events O an optimistic completion time O the likelihood of various
The Swine
asked
Nov 26, 2024
by
The Swine
8.4k
points
Business
high-school
1
answer
4
votes
221k
views
asked
Jun 1, 2019
34.1k
views
The table shows five activities (in days) for a project. Use PERT (Program Evaluation and Review Technique) to calculate the expected time of completion for activity B. A. 11 days B. 6.5 days C. 9 days
Ahazzah
asked
Jun 1, 2019
by
Ahazzah
7.9k
points
Mathematics
middle-school
2
answers
3
votes
34.1k
views
asked
Jan 4, 2024
147k
views
The most time‑consuming path in a PERT network is called the: a) Slack path b) Completion path c) Critical path d) none of the above
Samuel Clay
asked
Jan 4, 2024
by
Samuel Clay
7.8k
points
Business
high-school
1
answer
3
votes
147k
views
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
9.5m
questions
12.2m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
i have a field 60m long and 110 wide going to be paved i ordered 660000000cm cubed of cement how thick must the cement be to cover field
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org