93.3k views
0 votes
a worker A finishes a project on his own in 12 days. the worker completes the same work alone in 16 days. the two workers started working together, but after 3 days A leaves and B. continues on his own. How many days will B need to finish the rest of the work?

1 Answer

4 votes

Answer:

Worker B needs 9 days to finish the rest of the work

Explanation:

Proportions

Worker A finishes a project on his own in 12 days and worker B does the same in 16 days.

Worker A does 1/12 of the project in one day and worker B does 1/16 of the project in one day. When working together, they do


(1)/(12)+(1)/(16)=(7)/(48)

After 3 days they have completed:


3*(7)/(48)=(7)/(16)

parts of the project, this means it still remains:


1-(7)/(16)=(9)/(16)

parts of the project and it is done by B alone. Since B does
(1)/(16) per day, he now takes


\displaystyle ((9)/(16))/((1)/(16))=9

days to complete the project.

Worker B needs 9 days to finish the rest of the work

User Avery Freeman
by
7.8k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.