Answer:
Option (b) $97,500
Step-by-step explanation:
Data provided in the question:
Salary of each inspector = $75,000
Time spend by one inspector on inspecting parts = 100%
Time spend by other inspector on inspecting parts = 30%
Time spend by other inspector on inspecting final product = 100%
Now,
The labor cost that should be assigned to the activity, inspecting parts is
= 100% of salary of one inspector + 30% of the salary of the other inspector
= $75,000 + ( 30% of $75,000 )
= $75,000 + ( 0.30 × $75,000 )
= $75,000 + $22,500
= $97,500
Option (b) $97,500