Final answer:
To determine how long it takes to produce the seventh ship in the LPD class, we can use the learning curve formula. Using the given information, it takes approximately 8,932 hours.
Step-by-step explanation:
To determine how long it takes to produce the seventh ship, we can use the learning curve formula. The formula is:
Time = Time for the first unit * (Number of units)^log(learning curve rate)
In this case, the time for the first unit is 32,355 hours and the number of units is 7. The learning curve rate is 85%. Plugging in these values, we get:
Time = 32,355 * (7)^log(0.85)
Calculating this, we find that it takes approximately 8,932 hours to produce the seventh ship.