All of the following elements should be included in a project scope statement EXCEPT: ​ a. final and intermediate deliverables with acceptance criteria b. names of the project team members c. constraints imposed on the project, and assumptions made during planning d. project boundaries or exclusions

User Lear
by
5.3k points

1 Answer

3 votes

Answer:

(b). Names of the project team members.

Step-by-step explanation:

The scope statement of a project may vary from one organization to another and it depends on the type of project to be implemented.

The project scope statement contains information such as; statement of the problem, goals and objectives of the project, requirements for the project, project deliverables, project constraints and exclusions not within the scope of the project.

However, the names of the project team members are not included in the project scope statement.