Answer:
The correct answer is B.
Step-by-step explanation:
Giving the following information:
Setup costs $200,000 Number of setups 250
Ordering costs 80,000 Number of orders 1,600
Maintenance 400,000 Machine hours 2,000
Power 40,000 Kilowatt-hours 40,000
Job 6A
Units completed 100
Direct labor hours 50
Number of setups 1
Number of orders 4
Machine hours 20
Kilowatt-hours 30
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate:
Setup= ($200,000/250)= 800 per set up
Ordering costs= (80,000/1,600)= 50 per order
Maintenance= (400,000/2,000)= 200 per machine hour
Power= (40,000/40,000)= $1 per kilowatt hour
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Job 6A:
Set up= 800
Ordering= 50*4= 200
Maintenance= 200*20= 4000
Power= 30
Total= $5030