Answer:
desired cycle time: 60 seconds
Step-by-step explanation:
The desired cycle time should match production with demand
If there is a demand per day of 480 units then the cycle time should be:
8 hours x 60 minute x 60 seconds = 28,800 second
we divide this by the 480 units of demand:
28,800 second/ 480 units = 60
The company needs to complete a unit in a 60 second time period.