During the supplier selection phase of the supplier relationship​ process, a starting point for selecting suppliers is to perform a total cost analysis. Which of the following is a key cost to consider for each​ supplier?

A. hiring costs
B. expansion costs
C. material costs
D. All of the above.

User Tcurdt
by
8.2k points

1 Answer

1 vote
D) All of the above