Answer:
The predetermined overhead rate is 42 $/h.
Step-by-step explanation:
The predetermined overhead rate is calculated by the estimated manufacturing overhead divided by the estimated machine hours.
Predetermined overhead rate = $357000/8500h = 42 $/h