Answer:
direct labor cost variance = 14150 U
correct option is C) $14,150 U
Step-by-step explanation:
given data
labor hours LH = 1,000
actual labor cost AL = $48.15 per hour
standard cost SC = $34 an hour
labor cost totaling = $26,000
to find out
direct labor cost variance
solution
solution
we will apply here equation for direct labor cost variance that is
direct labor cost variance = LH × ( AL - SC) ..............1
here LH is labor hours and AL is actual labor cost and SC is standard cost so put all these in equation 1
we get
direct labor cost variance = 1000 × ( 48.15 - 34 )
direct labor cost variance = 14150 U
correct option is C) $14,150 U