145k views
5 votes
Tier, Inc. had actual manufacturing overhead costs of $1,210,000 and a predetermined overhead rate of $4.00 per machine hour. Tiger, Inc. worked 290,000 machine hours during the period. Tiger's manufacturing overhead is:a. $50,000 overappliedb. $50,000 underappliedc. $60,000 overappliedd. $60,000 underapplied

1 Answer

4 votes

Answer:

The correct answer is B: $50000 underapplied

Step-by-step explanation:

Giving the following information:

Tier, Inc. had actual manufacturing overhead costs of $1,210,000 and a predetermined overhead rate of $4.00 per machine hour. Tiger, Inc. worked 290,000 machine hours during the period.

The manufacturing overhead applied is= 4*290000=$1,160,000

Actual overhead= $1,210,000

Variance= 1,210,000 - 1,160,000= 50000 underapplied

It was underapplied because it incurred in higher manufacturing overhead costs.

User Chrisbro
by
8.1k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.