Answer:
Efficiency will be 0.75 so option (c) will be correct option
Step-by-step explanation:
We have given Total time for all task = 60 minutes
Actual Number of workstations = 8
Cycle time = 10 minutes
Efficiency is given by
![Efficiency(\eta ) =(total\ time\ for\ all\ task)/(number\ of\ work\ station* cycles\ time)=(60)/(8* 10)=0.75](https://img.qammunity.org/2020/formulas/business/high-school/xh1a2hkwbl6s6k3e7hbyja66hpi0vc8a3q.png)
So option (c) will be the correct option