Answer:
Efficiency will be 0.75 so option (c) will be correct option
Step-by-step explanation:
We have given Total time for all task = 60 minutes
Actual Number of workstations = 8
Cycle time = 10 minutes
Efficiency is given by

So option (c) will be the correct option