The following data have been recorded for recently completed Job 323 on its job cost sheet. Direct materials cost was $2,260. A total of 37 direct labor-hours and 141 machine-hours were worked on the job. The direct labor wage rate is $13 per labor-hour. The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $14 per machine-hour. The total cost for the job on its job cost sheet would be:$3,259$2,741$4,715$2,287

User CarlM
by
6.0k points

1 Answer

4 votes

Answer:

The correct answe is $4715

Step-by-step explanation:

First, we need to accommodate the information provided:

Job 323:

direct materials= $2260

direct labor hours= 37

machine hours= 141

The cost of direct hours is $13. Based on a predetermined overhead rate, machine hours cost $14.

Total cost for the job= 2260+ 37*13 + 141*14

Total cost for the job= $4715.