_________ is the biggest problem you can face if you don’t identify the scope of your risk management project. Scope creep Noncompliance System failure Nonrepudiation

User Jbcaveman
by
4.4k points

1 Answer

4 votes

Answer: Scope creep

Step-by-step explanation:

Scope creep in the project management basically refers to the uncontrolled development or growth in the project creep. It basically occur when the project scope are not appropriately defined.

It usually involve lack of change in the control system and increase the complexity of the project. It is also has poor requirement analysis.

So, that is why it is the biggest problem we usually face in the project management.