Answer:
A) $56,000
Step-by-step explanation:
Provided information,
Total overheads
Factory maintenance = $96,000
Rent on factory building = $180,000
Utility = $44,000
Total overheads = $320,000
Total labor hours of each product
Product X = 700
2 = 1,400 hours
Product Y = 2,000
3.3 = 6,600 hours
Total hours = 8,000
Overheads allocated to product X based on labor hours =
Therefore correct option is
A) $56,000