Answer:
A) $56,000
Step-by-step explanation:
Provided information,
Total overheads
Factory maintenance = $96,000
Rent on factory building = $180,000
Utility = $44,000
Total overheads = $320,000
Total labor hours of each product
Product X = 700
2 = 1,400 hours
Product Y = 2,000
3.3 = 6,600 hours
Total hours = 8,000
Overheads allocated to product X based on labor hours =
![(320,000)/(8,000) *\: 1,400 = 56,000](https://img.qammunity.org/2020/formulas/business/college/g7x3fu7agje7kabxdc5f57ubfd9ewc50bq.png)
Therefore correct option is
A) $56,000