Answer:
Given:
January 1 :
Materials = $11,000
Work in Process = $19,800
Finished Goods = $23,100
December 31 :
Materials = $8,800
Work in Process = $18,700
Finished Goods = $18,150
Also,
Direct labor costs = $33,000
Manufacturing overhead = $46,200
Materials purchased = $29,700