Answer:
A.- 3.45 min to produce two work units
B.- In a 8-hout shift at standard performance 274 work units are produced
Step-by-step explanation:
The Standart tiem per piece would be:
![StandardTime=NormalTime*(1+PFD)](https://img.qammunity.org/2020/formulas/business/college/tovngkfc7kju71s4ysx3gi9foofuhidpd0.png)
Given your numbers it will be:
![3 * (1 + 0.15)= 3.45](https://img.qammunity.org/2020/formulas/business/college/56ns5gn91cig0rla6fd5dh6p2qgdg0zc3x.png)
This is the time per cycle to produce 2 work units
Now, in an 8 hours shift there are 480 minutes. Dividing between the standard time of a cycle we get the standard performance
![(480)/(3.45) = 137.14](https://img.qammunity.org/2020/formulas/business/college/oq8g3sv3romqoyzga8di2x77whlej9eoi2.png)
Rounding, we will be getting 137 cycles
Lastly, because each cycle produce 2 work units we are having a total of 274 Units