Answer:
the difference between the budgeted and the actual manufacturing overhead using job costing is $0.50 per hour
Step-by-step explanation:
The computation of the difference between the budgeted and the actual manufacturing overhead using job costing is shown below
The rate based on the actual one
= $450,000 ÷ 50,000
= $9 per hour
The rate based on the standard one
= $340,000 ÷ 40,000
= $8.50 per hour
Now the difference between them is
= $9 - $8.5
= $0.50 per hour
Hence, the difference between the budgeted and the actual manufacturing overhead using job costing is $0.50 per hour