Answer:
the material quantity variance
Step-by-step explanation:
As we know that
Material quantity variance is
= (Standard quantity - actual quantity) × standard price
This represent that the difference between the standard quantity and the actual quantity should be multiplied with the standard price is known as the material quantity variance
Therefore as per the given situation, the material quantity variance is the answer