Answer:
30 days
Explanation:
The above question is solved as shown below:
Working together Team Z and Y can do the same work in 14 days.
1/Team Y + 1/Team Z = 1/14 days
Team Z can do the work in 26 days,
Hence:
1/Team Y + 1/26 days = 1 /14 days
= 1/ Team Y + 1/26 = 1/14
1/Team Y = 1/14 - 1/26
The Lowest Common Denominator = 182
Hence:
1/Team Y = 13 - 7/182
1/Team Y = 6/182
Cross Multiply
Team Y × 6 = 1 × 182
Team Y = 182/6
Team Y = 30.33 days
Approximately to the nearest whole number = 30 days
Therefore, Team Y alone can do the job in 30 days