The first unit of a job took 40 hours to complete. The work has a learning percentage of 88. The manager wants time estimates for units 2, 3, 4, and 5. Develop those time estimates.
asked
Apr 9, 2021
126k
views
5
votes
The first unit of a job took 40 hours to complete. The work has a learning percentage of 88. The manager wants time estimates for units 2, 3, 4, and 5. Develop those time estimates.
Business
college
Ttsesm
asked
by
Ttsesm
6.9k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
0
votes
Answer:
im confused on that one
Step-by-step explanation:
Hsinxh
answered
Apr 15, 2021
by
Hsinxh
6.5k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
7.4m
questions
9.9m
answers
Other Questions
In what way did the GI Bill contribute to the growth of professional and white-collar jobs ? A.by providing US laborers with new job-training programs B.by giving US veterans assistance to purchase a new
What is meant by data mining ?
What is the best way to describe a stock market?
You sell popcorn during your schools football games. Knowing that the people usually buy more when the price is lower, how would you price your popcorn after halftime?
Identify the advantages and disadvantages of a command economy.
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org