Answer:
$153,900
Step-by-step explanation:
With regards to the above, we need to first calculate the overhead per hour
Overhead cost per hour = ($135,000 + $36,000)/200,000 = $0.855
Now, we can calculate the total cost of 180,000 hours
Overhead cost = 180,000 × $0.855
Overhead cost = $153,900
Therefore, flexible budget for these total cost is $153,900