Suppose your PV for a project was $100,000 and your EV was $70,000. Your SPI for this project would be

1 Answer

4 votes

Answer:

Schedule performance index = 0.7

Step-by-step explanation:

Schedule performance index = EV / PV

Schedule performance index = $70,000 / $100,000

Schedule performance index = 0.7

The Schedule performance index is less than 1 and this indicates that the project performance is unfavorable and behind the schedule for completion .

SPI = 1 (Project on schedule), SPI<1 (Project behind the schedule).