Answer:
If they work together, they will take 6.16 days.
Explanation:
Elsa takes 14 days to complete the work.
So, 1 day work by Elsa is

Anna takes 11 days to complete the work.
So, 1 day work by Anna is
.
So, Let if they work together, it would take x number of days.
So, we can set up equation as

Find LCD, which is 154.

Simplify

Cross multiply,
25x=154
Divide both sides by 25
x=6.16 days
If they work together, they will take 6.16 days.