9 men working in a factory produce a. certain number of pans in 6 working days. how long will it take 12 men to produce the same number of pans if they work at the same rate?​

User Esparver
by
7.8k points

1 Answer

4 votes

Answer:

It would take 12 men 4.5 (four and a half) days to do the same amount of work as the 9 men in 6 days.

Explanation:

9 is 75% of 12 (12*.75=9) if they work at the same rate it would take 75% of the time it did for the 9 men (6hrs*.75=4.5)