164k views
4 votes
You have reached the planned half way mark. The total planned cost at this stage is five hundred dollars. The actual physical work that has been completed at this stage is worth $400. You have already spent one thousand dollars on the project. What is the CPI?

1 Answer

5 votes

Answer:

0.4

Step-by-step explanation:

Calculation for the CPI

Using this formula

CPI = Actual physical work/Amount spent on the project

Let plug in the formula

CPI=$400/$1,000

CPI=0.4

Therefore the CPI will be 0.4

User Max Yari
by
4.9k points