Answer:
C. 157
Step-by-step explanation:
Safety stock = Z-score * Standard deviation of average demand * √lead time
Z-score for 74 % service level is 0.643
Standard Deviation of demand is 200
Lead Time = 1.5 weeks
Safety stock = 0.643 * 200 * √1.5
Safety stock = 0.643 * 200 * 1.224745
Safety stock = 157.502