Answer:
the labor rate variance is $16,000 unfavorable
Step-by-step explanation:
The computation of the labor rate variance is shown below:
As we know that
Labour Rate Variance = ( Actual Rate - Standard Rate) ×Actual Hours Worked
= ($160,000 ÷ 22,000 direct labor hours - $8) × 22000 direct labor hours
= ($7.27 - $8) × 22000 direct labor hours
= $16,000 Unfavorable
hence, the labor rate variance is $16,000 unfavorable
We simply applied the above formula so that the correct value could come
And, the same is to be considered