Answer: $310,000
Step-by-step explanation:
Based on the information given in the question, the cost of jobs that are completed in February will be:
Direct materials issued to production = $90,000
Add: Direct labor cost = $107,000
Add: Manufacturing overhead applied = $113,000
This will be:
= $90,000 + $107,000 + $113,000
= $310,000