The time taken to build a house is inversely proportional to the number of builders. If there are 6 builders, it takes 80 days to complete the house. How many builders must be e…
asked
Aug 23, 2021
16.7k
views
0
votes
The time taken to build a house is inversely proportional to the number of builders.
If there are 6 builders, it takes 80 days to complete the house.
How many builders must be employed to build the house in just 16 days?
Mathematics
college
Zey
asked
by
Zey
8.4k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
2
votes
Answer:
30 builders
Explanation:
80÷5=16
6x5=30
Amit Jangid
answered
Aug 27, 2021
by
Amit Jangid
7.7k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
← Prev Question
Next Question →
No related questions found
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
9.4m
questions
12.2m
answers
Categories
All categories
Mathematics
(3.7m)
History
(955k)
English
(903k)
Biology
(716k)
Chemistry
(440k)
Physics
(405k)
Social Studies
(564k)
Advanced Placement
(27.5k)
SAT
(19.1k)
Geography
(146k)
Health
(283k)
Arts
(107k)
Business
(468k)
Computers & Tech
(195k)
French
(33.9k)
German
(4.9k)
Spanish
(174k)
Medicine
(125k)
Law
(53.4k)
Engineering
(74.2k)
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search Qammunity.org