Answer:
Option A is:
3000+750x=9,000
Option B:
9000= 1000(9)
Explanation:
X is the number of months it would take in option A. Option A would take 8 months while the other option takes 9. Option A you only pay 750 monthly while option B you ay 1000 monthly