Answer:
3,000 yd3 = 200 dtl
Chapter 1: Problem Solving 17 / 21
Rates Question
12 A highway had a landslide, where 3,000 cubic yards of material fell on the road, requiring 200 dump truck loads to clear. On another highway, a slide left 40,000 cubic yards on the road. How many dump truck loads would be needed to clear this slide?
3,000 yd3 = 200 dtl
40,000 yd3 × 200 dtl = 2,667 dtl
3, 000 yd3