Answer:
Cost per cubic yard to place concrete using each of the following alternatives:
Alternative a = $14.04
Alternative b = $14.71
Step-by-step explanation:
a) Data and Calculations:
Work of concrete in footings = 140 cubic yards
a. Price of using crane and bucket = $225 per hour
Number of hours required for this setup = 7 hours
Transportation of the crane = $390
Therefore, total cost under this alternative = $1,965 (($225*7) + $390)
Cost per cubic yard = $14.04 ($1,965/140)
b. Price of using a concrete pump = $295 per hour
Number of hours required for this setup = 6 hours
Transportation of the pump = $290
Therefore, total cost under this alternative = $2,060 (($295*6) + $290)
Cost per cubic yard = $14.71 ($2,060/140)