Answer:
0.3727
Explanation:
From the given information
Total costs = Project cost + Flotation cost
Total costs = $35,000,000 + $2,200,000
Total costs = $37,200,000
Amount raised × (1 – fT) = Amount needed after flotation costs
$37,200,000 × (1 – fT) = $35,000,000
1 - fT = $35,000,000 / $37,200,000
1 - fT = 0.9409
fT = 1 - 0.9409
fT = 0.0591
wD + wE = 1
wD = 1 - wE
where;
wD = weight of debt
wE = weight of equity
WAFC = (wD × Debt's fT) + (wE × Equity's fT)
0.0591 = (wD × 0.03) + ( (1 - wD) × 0.07)
0.0591 = [wD × 0.03) + 0.07 - (wD × 0.07)
0.0591 - 0.07 = -(wD × 0.04)
-0.0109 = - (wD × 0.04)
wD = -0.0109 / -0.04
wD = 0.2715
wE = 1 - wD
wE = 1 - 0.2715
wE = 0.7285
The debt-equity ratio = wD / wE
The debt-equity ratio = 0.2715 / 0.7285
The debt-equity ratio = 0.3727