If 5 workers complete one task in 7 days, then how many days will 7 workers take to complete the same task?

User Samrockon
by
4.9k points

1 Answer

4 votes

Answer: 5 days

Explanation:

5*7=35 - means the total amount of the days to complete the job by 1 worker is 35 days

So 7 workers can do this job in

35:7=5 days