With a planned volume of 15,000 units, the master budget includes variable costs of $450,000 and fixed costs of $350,000. If the actual volume is 12,000 units, the total costs under flexible budget should be:__________a. $490,000.b. $560,000.c. $650,000.d. $710,000.

User Talat
by
5.2k points

1 Answer

6 votes

Answer:

Total cost= $710,000

Step-by-step explanation:

Giving the following information:

15,00 units:

Fixed costs= $350,000

Total variable cost= $450,000

First, we need to calculate the unitary variable cost:

Unitary variable cost= 450,000 / 15,000

Unitary variable cost= $30

Now, the total cost for 12,000 units:

Total cost= 350,000 + 30*12,000

Total cost= $710,000