A sewing company planned to produce 4,500 dresses in 25 days.

However, they produced 20 more dresses each day than
planned, and as a result finished the job earlier than sche
many days early did they finish the job?

User Jhurliman
by
2.9k points

1 Answer

29 votes
29 votes

Answer:

2.5 days

Explanation:

The planned production rate was ...

(4500 dresses)/(25 days) = 180 dresses/day

The actual production rate was ...

180 dresses/day + 20 dresses/day = 200 dresses/day

So the actual time required for production of 4500 dresses was ...

(4500 dresses)/(200 dresses/day) = 22.5 days

That is the time required was less by ...

25 days -22.5 days = 2.5 days

The company finished 2.5 days early.