67.3k views
0 votes
A project has an initial cost of $10,600 and produces cash inflows of $3,700,$4,900,and $2,500 for Years 1 to 3,respectively.What is the discounted payback period if the required rate of return is 7.5 percent?

A) 2.65 years
B) 2.78 years
C) 2.94 years
D) 2.88 years
E) Never

User Egan Wolf
by
4.2k points

1 Answer

1 vote

Answer:

The project will never pay the initial investment.

Step-by-step explanation:

The payback period is the time required to cover the initial investment.

We need to use the following formula on each cash flow:

PV= Cf/(1+i)^n

PV1= 3,700/1.075= 3,441.86

PV2= 4,900/1.075^2= 4,240.13

PV3= 2,500/1.075^3= 2,012.40

Now, the payback period:

Year 1= 3,441.86 - 10,600= -7,158.14

Year 2= 4,240.13 - 7,158.14= -2,918

Year 3= 2,010.4 - 2,918= -907.6

The project will never pay the initial investment.

User Sveisvei
by
3.2k points