Answer:
a)
small facility:
initial outlay = -$9,000,000
present value of expected cash flows = (0.6 x $9,000,000) + (0.4 x $12,000,000) = $10,200,000
NPV = $10,200,000 - $9,000,000 = $1,200,000
large facility:
initial outlay = -$10,000,000
present value of expected cash flows = (0.6 x $12,000,000) + (0.4 x $15,000,000) = $13,200,000
NPV = $13,200,000 - $10,000,000 = $3,200,000
b) the best option is:
- a. to build the large facility.
the NPV of the large facility is significantly higher than the NPV of the smaller facility, while the required investment is not that different.