Answer:
the number of days for the current lead time is 5 days
Explanation:
The computation of the number of days for the current lead time is shown below:
Given that
According to Littles law,
Lead Time = Work in Progress ÷ Average Completion Rate
where,
Work in Progress = 20 quotes
And,
Average completion rate = 4 quotes per day
So lead time is
= 20 quotes ÷ 4 quotes
= 5 days
Hence, the number of days for the current lead time is 5 days