90.6k views
3 votes
A quoting department for a national publishing house completes 4 quotes per day, and there are 20 quotes in various stages in the department. Applying Little’s Law, the current lead time for a quote is how many days?

1 Answer

6 votes

Answer:

the number of days for the current lead time is 5 days

Explanation:

The computation of the number of days for the current lead time is shown below:

Given that

According to Littles law,

Lead Time = Work in Progress ÷ Average Completion Rate

where,

Work in Progress = 20 quotes

And,

Average completion rate = 4 quotes per day

So lead time is

= 20 quotes ÷ 4 quotes

= 5 days

Hence, the number of days for the current lead time is 5 days

User Rlivsey
by
4.9k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.