Answer:
a. The present value of the Project A1 is $7,643.69
b. The value of X is $24,264.29
c. The project balance for project A1 at the end of year 3 is $11,625.29
d. Project A2 should be selected
Step-by-step explanation:
Note: The complete question is attached below
a. PV = -P + ∑F/(1+i)^n
Pv = -15,000 + 9,500/(1+0.15)^1 + 12500/(1+0.15)^2 + 7500/(1+0.15)^3
PV = -15,000 + 9500/1.15 + 12500/1.3225 + 7500/1.5209
PV = -15000 + 8261.2 + 9451.24 + 4931.25
PV = $7,643.69
The present value of the Project A1 is $7,643.69
b. It is given thar PV worth A2 = 9300, initial investment 25000, rate of interest = 15%
PV = -P + ∑F/(1+i)^n
Pv = -25000 + 0/(1+0.15)^1 + X/(1+0.15)^2 + X/(1+0.15)^3
9,300 = -25000 + 0 + X/1.3225 + X/1.5209
9,300 + 25000 = 0.7561(X) + 0.6575(X)
34300 = 1.4136(X)
X = 34300 / 1.4136
X = $24,264.29
The value of X is $24,264.29
c. Future value = Present value(1+i)^n
Future value = 7643.69*(1+0.15)^3
Future value = 7643.69*1.5209
Future value = 11,625.29
The project balance for project A1 at the end of year 3 is $11,625.29
d. Since the PV of project A2 ($9,300) is greater than the pre project($7643.69), Project A2 should be selected